October 27, 2015

The framers have been busy! What was once an empty space, is now filled with the outlines of new offices, restrooms and our coffee shop. The electrician has also been busy right alongside the framer, getting all the new sockets, phone and data lines, and circuits prepped and ready. The mechanical sub (air conditioning) has been buys hanging ductwork into every space so that we can stay nice and comfy!
While working on installing our new AC units on the roof, we discovered an area of the roof that had been damaged by water that wasn’t caught in our initial inspection. The roofer will be repairing this section of the roof and the plumber will add a few more drains so we will be ready for this WET winter season!
Next up is drywall!
IMG_0973 IMG_0974 IMG_0975 IMG_0976 IMG_0977 IMG_0978 IMG_0979 IMG_0980 IMG_0981 IMG_0982 IMG_0983 IMG_0984 IMG_0985 IMG_0986

Leave a Reply